The Building Control Process
-
Design Stage: We assess initial drawings and
basic concepts to ensure that the principles of the work comply
with the Building Regulations. Where pre-application advice is
sought, we will also consult the relevant statutory bodies,
such as the Fire Authority and Water Authority.
-
Application Submission: We collate all
information for submission (as per our New Application
Checklist), with the Initial Notice, to the Local Authority.
-
Plans Checking: We ensure that all plans
comply with the Regulations and carry out a Statutory
Consultation with the Fire Authority.
-
Site Inspections: We observe progress on site,
with a pre-planned and agreed inspection framework identifying
and resolving any issues that may arise during construction .
-
Completion: We issue a Final Certificate,
confirming that the finished project complies with the Building
Regulations.
For further information please contact: Paul Timmins/Andrew Maple
on 020 7491 1914.